Zuoz station is set to undergo extensive refurbishment between 2025 and 2027 to ensure it meets today’s requirements for modern, accessible and future-oriented rail transport. The focus is on improved access, greater comfort for passengers and a state-of-the-art infrastructure.
Two new Perrons, each 225 metres long, are planned. Both Perrons will be connected by a new pedestrian underpass. At the same time, all technical systems throughout the station area will be upgraded. These include, amongst other things, the catenary systems, lighting, and signalling and signal box technology. A new technical building will be constructed to house the necessary railway technology; this will form part of the new pedestrian underpass and will be accessed from it.
These measures will enhance Zuoz station in a sustainable manner and ensure it is equipped for the coming decades.
Milestones
Period
March - November 2026
Construction of a retaining wall on the river side
1–5 June 2026
Adjustment of track geometry (night work)
6–7 June 2026
During full closure: Construction of pedestrian underpass (3-shift operation)
July - November 2026
Construction of the platform roof on the village side
December 2026 – March 2027
Winter break
March – May 2027
Construction of a platform roof on the river side
12 April – 14 May 2027
During the total closure: construction of Perrons, new tracks, new lighting and new passenger information systems
15 May 2027
Opening of the pedestrian underpass and Perrons
May – October 2027
Finishing work
Visualisations





Information for local residents
During the construction period, there may be some disruption caused by the works. This includes temporary construction noise, site traffic and occasional restrictions in the vicinity of the station. The works will be carried out in concentrated phases wherever possible to minimise disruption to local residents.
The construction site organisation is designed to ensure that access to the neighbourhood and to adjacent properties is maintained at all times. Information regarding noisy work and specific construction phases will be provided in good time.
Information for passengers
During the construction work at Zuoz station, there may be changes to routes, temporary Perrons or alterations to access points.
Some parts of the station refurbishment project will require complete closures of the track between Zernez and Samedan. These complete closures will take place during the following period:
Saturday, 6 June 2026 to Sunday, 7 June 2026
Monday, 12 April 2027 to Saturday, 15 May 2027
Up-to-date information on timetables and alternative services can be found in the online timetable.