Projects and dossiers

Landquart station

Renovation and conversion from 2018 to 2032

Rhaetian Railway is currently in a far-reaching modernisation phase and has invested heavily in the renewal of its vehicle fleet and infrastructure facilities in recent years. The new rolling stock consists increasingly of railcars and articulated trains, which are no longer separated during maintenance, which is why the existing workshops have to be adapted to the new rolling stock. The changes affect not only the workshops themselves, but also large areas in and around Landquart station.

The major project “Renovation and conversion of Landquart Station” consists of various interrelated sub-projects, which are being carried out in stages. The first construction work began in May 2018. An investment volume of more than CHF 700 million has been estimated for this major project.

Current sub-project

Expansion of track and platform facilities – Phase B

The track and Perron facilities are currently being upgraded as part of Phase B. At the heart of the project is the shared central Perron, designed to make changing between RhB and SBB trains more convenient and quicker. The shared Perron allows for the addition of one extra track with a Perron for each railway. This lays the foundation for the planned half-hourly service. In addition, the track and Perron facilities are being modernised and, where necessary, extended to accommodate the RhB’s new fleet of rolling stock.

The Perrons will be fitted with new, uniform roofs on which translucent photovoltaic systems will be installed. The new installations create a pleasant, bright atmosphere and, thanks to their large surface area, make a significant contribution to sustainable electricity generation. The new Perrons will be connected by a wide and well-lit pedestrian underpass. For the goods railway, receiving and shunting tracks will be extended on both lines. To ensure the new tracks can be operated safely, a new shared railway engineering building will also be constructed at the northern end of the Perron.

Period

Work

April – December 2026

Installation sites, underground cabling works, foundations

May – October 2026

Civil engineering works on the office building

November 2026 – July 2027

Building construction work on the administrative building

March 2027 – August 2028

New pedestrian underpass

January 2027 – November 2029

New SBB bridge at Landquart "Left" (new Track 8)

March 2027 – May 2028

Construction of the new RhB bridge at Landquart (new tracks 1–3)

March 2027 – January 2032

Track works on the RhB

October 2027 – July 2030

SBB track works

May 2028 – March 2029

New entrance to Red Square

June 2028 – November 2032

Construction of new platform facilities, including stairways and ramps

April – November 2030

Renovation of the SBB Landquart Bridge (Right) (New Track 11)

October 2030 – December 2031

Renovation of the SBB Landquart "Left" Bridge (new Track 9)

June – November 2031

Insert RhB Landquart Bridge (Tracks 1–3, new)

January – December 2032

Dismantling of installation sites and project completion