Rhaetian Railway is currently in a far-reaching modernisation phase and has invested heavily in the renewal of its vehicle fleet and infrastructure facilities in recent years. The new rolling stock consists increasingly of railcars and articulated trains, which are no longer separated during maintenance, which is why the existing workshops have to be adapted to the new rolling stock. The changes affect not only the workshops themselves, but also large areas in and around Landquart station.
The major project “Renovation and conversion of Landquart Station” consists of various interrelated sub-projects, which are being carried out in stages. The first construction work began in May 2018. An investment volume of more than CHF 700 million has been estimated for this major project.
Current sub-project
Expansion of track and platform facilities – Phase B
The track and Perron facilities are currently being upgraded as part of Phase B. At the heart of the project is the shared central Perron, designed to make changing between RhB and SBB trains more convenient and quicker. The shared Perron allows for the addition of one extra track with a Perron for each railway. This lays the foundation for the planned half-hourly service. In addition, the track and Perron facilities are being modernised and, where necessary, extended to accommodate the RhB’s new fleet of rolling stock.
The Perrons will be fitted with new, uniform roofs on which translucent photovoltaic systems will be installed. The new installations create a pleasant, bright atmosphere and, thanks to their large surface area, make a significant contribution to sustainable electricity generation. The new Perrons will be connected by a wide and well-lit pedestrian underpass. For the goods railway, receiving and shunting tracks will be extended on both lines. To ensure the new tracks can be operated safely, a new shared railway engineering building will also be constructed at the northern end of the Perron.
Information for local residents
Sleep disturbances
Period
Work
April – December 2026
Installation sites, underground cabling works, foundations
May – October 2026
Civil engineering works on the office building
November 2026 – July 2027
Building construction work on the administrative building
March 2027 – August 2028
New pedestrian underpass
January 2027 – November 2029
New SBB bridge at Landquart "Left" (new Track 8)
March 2027 – May 2028
Construction of the new RhB bridge at Landquart (new tracks 1–3)
March 2027 – January 2032
Track works on the RhB
October 2027 – July 2030
SBB track works
May 2028 – March 2029
New entrance to Red Square
June 2028 – November 2032
Construction of new platform facilities, including stairways and ramps
April – November 2030
Renovation of the SBB Landquart Bridge (Right) (New Track 11)
October 2030 – December 2031
Renovation of the SBB Landquart "Left" Bridge (new Track 9)
June – November 2031
Insert RhB Landquart Bridge (Tracks 1–3, new)
January – December 2032
Dismantling of installation sites and project completion