The following two tables include the main completion deadlines, along with other key facts and figures.
Facts and figures | |
---|---|
Planning and completion | 14 years (2011–2024) |
Construction period | 10 years |
Length of Albula Tunnel II (new construction) | 5,860 m |
Length of Albula Tunnel I (existing structure) | 5,864 m |
Transverse access links to safety tunnel | 12 |
Height of tunnel from top edge of rail (opening) | 5,44 m (9,52 m) |
Inner width of tunnel (opening) | 5,76 m (7,67 m) |
Maximum cross-sectional area of opening | 58,39 m² |
Free cross-sectional area of tunnel | 26,88 m² |
Maximum altitude | 1,821 metres above sea level |
Maximum top speed in tunnel | 120 km / h |
Total cost of project | CHF 407 million |
Finance | federal government 100% |
Volume of excavation | 244,000 m3 (solid material) |
Trains per year | 15,215 |
Annual passenger traffic | 1.5 million |
Various drilled samples of the geological layers of the Albula massif.
Deadlines | |
---|---|
Preparation work | 2014 |
Cutting of first turf | June 2014 |
Main preliminary operations | 2015 – 2018 |
Completion of tunneling | October 2018 |
Completion of the tunnel shell | 2022 |
Installation of the track and the catenary | 2023 |
Installation of the railway technology | 2023 – 2024 |
Completion of project | June 2024 |
Restoring to nature / demolition | 2021 – 2024 |
Renovation of the evacuation passage | 2024 – 2026 |